United States
Cherrywood Labs
This project encompasses the comprehensive transformation of Building 10 at The Campus in Cherrywood. The objective is to create state-of-the-art life science laboratories, modern offices, meeting spaces, event facilities, a canteen, equipment rooms, and all associated infrastructure. The scope of work includes:
- Construction of life science laboratories, comprising 6 main labs and 11 starter labs, along with 15 separate offices, a kitchen, canteen, function room, and goods storage areas. This involves the installation of new partition walls, ceilings, glazed screens, floor finishes, doors, frames, architraves, skirtings, acoustic and fire barriers, and furniture setup.
- Installation of flue stacks and associated cladding, including all necessary components, flashings, fixings, and structural elements.
- Adjustment of curtain walling and window systems, including the creation of new upstands and blockwork as needed.
Mechanical works encompass:
- Installation of new internal ducting.
- Installation of fan coil units, air handling units, ventilation systems, and fume extractors.
- Associated enhancements to the flue exhaust system.
- Installation of plumbing, waste, and gas services.
Electrical works include:
- Installation of new electrical fittings for power and data.
- Installation of light fittings as required to match the new floor layout.
- Installation of smoke detectors and fire alarm panels.
- Installation of data and electrical trunking for workstations.
- Provision of a new power supply to accommodate the new workstation layouts.
- Installation of WIFI points, AV systems, and security infrastructure to ensure a fully functional and secure workspace.
® DonalMurphyPhotography
COMPANY
sectors
services
Architect
Hypostyle
Client
Spear Street Capital
Location
Cherrywood Campus Loughlinstown, Co. Dublin
Square Foot
32,000sf
Contract Type
Lump Sum
Architect
Hypostyle
Project Engineer
OCSC
Owners Rep
Scollard Doyle
Quantity Surveyor
Scollard Doyle
No. of weeks to complete the project
18 weeks